Cisco WLAN and Infrastructure for Distribution Center
This London-based retailer is the world's premiere online luxury fashion boutique. When the company needed to establish a distribution center in northern New Jersey, they retained BBH Solutions to implement the technology infrastructure.
-
Distribution Center The 80,000 square foot distribution center required physical infrastructure and WLAN for operations and real-time inventory control.
This online retail women's boutique, launched in 2000, features editorial fashion content and serves over 2.5 million visitors per month. With steadily increasing sales, the company began construction of its first US distribution center in 2010.
Client's Challenge:
For phase one of this multi-phased project, the client required an integration partner that could perform technology services to make their systems operational on a short construction timeline.
BBH's Solution:
The client retained BBH Solutions for project management and installation services of the following technologies:
- Structured cabling system planning
- Installation, termination, and testing of Cat 5e copper cabling for 100 workstations
- Inter-cabinet fiber optic installation, termination, and testing
- APC data cabinet installation
- Installation of APC Smart-UPS 3000VA UPS systems in data cabinets
- Installation of Cisco core network infrastructure, including Catalyst 3750 switches, 2921 routers, and ASA 5505 firewall appliances
- WLAN installation: 11 Cisco Aironet 1140 Series wireless access points for full secure WLAN coverage
- De-installation and re-installation of 65 workstations
- On site support on day of cutover
Added Value:
The client had the benefit of working with a single source integrator that holds expertise in several technology disciplines, including structured cabling, Cisco network infrastructure, APC power solutions, and Cisco WLAN. BBH Solutions completed the project in a neat, professional, and timely manner. The BBH Solutions project team's experience in working with general contractors and other sub trades helped to bring the project to completion on a short construction schedule.